(***) For Tom Tucker’s Toffee in problem 4, draw a sawtooth diagram similar to the one in Figure…

 (***) For Tom Tucker’s Toffee in problem 4, draw a sawtooth diagram similar to the one in Figure 11.3. Assume that the beginning inventory level is equal to the restocking level and that the demand rate is a constant 7 tins per day. What is the safety stock level? (Hint: Look at the formula for calculating restocking level.) What is the average inventory level?

Problem 4:

4. (*) Jimmy’s Delicatessen sells large tins of Tom Tucker’s Toffee. The deli uses a periodic review system, checking inventory levels every 10 days, at which time an order is placed for more tins. Order lead time is 3 days. Average daily demand is 7 tins, so average demand during the reorder period and order lead time (13 days) is 91 tins. The standard deviation of demand during this same 13-day period is 17 tins. Calculate the restocking level. Assume that the desired service level is 90%.